ELLE FOURCHE, S.D. – The South Dakota Department of Transportation (SDDOT) says on Monday, March 20, 2023, bridge repair work is scheduled to begin in two locations including S.D. Highway 73 north of Howes over Cherry Creek and on U.S. Highway 212 east of Faith over Bear Creek.
With both bridge repair projects, traffic will be reduced to one lane at the bridges with stop signs at each end. Bridge work is expected to be completed by the end of May. This is the first phase of a project that will continue with milling and asphalt paving once the bridge work is complete.
The prime contractor on this $12.7 million project is Anderson Western, Inc. of Bismarck, ND. The overall completion date is Friday, Oct. 27, 2023.